FACILITY CONSTRUCTION SERVICES
Correction of Work/Warranty Management Plan
To download a copy of this document:
Microsoft Word Document - Right click here, choose "Save Target As" and download to your hard drive.
Adobe Acrobat File- Click here to view in browser or right-click to save a printable file. Requires the free Acrobat Reader. (Get it here.)
I. CORRECTION OF WORK
(Non conformance discovered less than one year after construction)
ACTIVITY
DEPARTMENT
ACTION
Evaluation
1
Maintenance
Respond to all calls
2
Maintenance
Evaluate problems and determine if cause is related to construction.
3
Maintenance
Repair routine maintenance problems on construction work completed less than one year.
Emergency Repairs*
1
Maintenance
Call contractor to respond to emergency work within agreed time
2
Maintenance
Repair emergency work and charge contractor if contractor cannot respond in required time or contractor fails to repair in agreed time.
3
Maintenance
Inform Facilities before and after making emergency repairs
4
Maintenance
Prepare documentation of calls, repairs, costs
5
Maintenance
Submit documentation to legal for reimbursement
Non-Emergency
Repairs
1
Maintenance
Call Facilities and request contractor repair
2
Facilities
Call contractor to respond within an agreed upon time
3
Maintenance
Meet contractor on site as necessary
4
Facilities
Coordinate repair with contractor
5
Facilities
Issue written notice of nonconformance
6
Facilities
Reach agreed upon completion date with contractor
7
Facilities
Give 7day written notice when work is not done by completion date.
8
Facilities
7days after written notice begin work through IDC and inform original contractor.
9
Facilities
Collect and submit documentation of calls/repairs/expenses for reimbursement
10
Facilities
Submit documentation to legal for reimbursement
1yr followup
1
Facilities
11months after substantial completion, arrange on site meeting with maintenance and school personnel to capture existing problems and give written notice to contractor before end of 12th month after substantial completion. (See also 4.2.14, supplemental conditions)
* Emergency repairs are those that are needed to reduce/prevent conditions detrimental to life/safety, further facility/equipment damage, or negatively impacting students learning.
CONTRACTUAL OBLIGATIONS:
CORRECTION OF WORK
AIA201
NOTES
1
Definitions
3.5.1
Materials, equipment, labor
2
Commencement of Substantial Completion
9.8.4
3
Architect provides admin. Svcs. During 1 yr. Correction of work period
4.2.1*
4.2.9
Warranties w/submittals
4
Contractor pays costs for failure to conform discoveries
12.2.1.1
5
Written notification of nonconformance required by owner to contractor within 1 yr. after substantial completion
12.2.2.1*
6
Extension of 1 yr for work not originally completed until after Substantial Completion
12.2.2.2
Submit documentation to legal for reimbursement
7
Other obligations of contractor after 1 yr period
12.2.5
Call Facilities and request contractor repair
*See AIA201 Supplemental Conditions prepared by Frank Mack
II. WARRANTY WORK
(Non conformance discovered less than one year after construction)
ACTIVITY
TYPE
DEPARTMENT
ACTION
Evaluation
1
Maintenance
Respond to all calls
2
Maintenance
Evaluate problems and determine if cause is related to construction.
Repairs
Equipment
1
Maintenance
Repair/replace and utilize manufacturer's warranty program.
Roofing Systems
1
Maintenance
Identify problem
2
Facilities
Coordinate repair through contractor as approved by roofing manufacturer bonding requirements
Construction systems (Localized problems)
1
Maintenance
Make repairs
(Systemic problems)
2
Maintenance
Coordinate site visit, solution and timeline with contractor.