District Timeline |
Event |
AIA 201
Reference |
Notes |
| 1 |
|
Contractor provides Punch list with request for substantial completion inspection |
AIA201, 9.8.2* |
|
| 2 |
|
Architect makes substantial completion inspection. |
4.2.9 |
Inspection |
| |
|
|
9.8.3* |
Inspection/Corrections required prior to substantial completion |
| |
|
Architect issues contractor/owner responsibilities |
9.8.4* |
|
| 3 |
X |
Architect issues Certificate of Substantial Completion |
4.2.9 |
|
| |
|
|
9.8.4* |
Establish date |
| 4 |
|
Architect prepares punch list |
9.8.7* |
Retainage (3 times the estimated cost of the punch list work) |
| |
|
|
9.8.9* |
Provision for no-fault punch list items |
| |
|
|
|
X-6 |
| 5 |
|
Contractor submits Application for payment for work to date |
4.2.5 |
X-6 |
| |
|
|
9.6.8* |
30,60,90 days after substantial completion |
| |
|
|
|
X-6 |
| 6 |
|
Architect issues Certificate for Payment for work to date |
4.2.5 |
X-6 |
| |
|
|
|
X-6 |
| 7 |
|
District makes progress payment |
|
X-6 |
| |
|
|
|
X-6 |
| 8 |
|
Contractor requests Final Inspection |
9.10.1 |
Written notice |
| |
|
|
|
|
| 9 |
|
Architect makes inspection |
4.2.9 |
|
| |
|
|
9.10.1 |
Inspection |
| 10 |
X+30 Days |
Architect determines date of final completion |
4.2.9 |
|
| |
|
|
9.8.8* |
Timing |
| 11 |
X+60 Days |
Penalty of incompleted punch list |
9.8.8* |
Timing & Liquidated Damages |
| 12 |
X+90 Days |
Penalty of incompleted punch list |
9.8.8* |
Timing & Liquidated Damages |
| 13 |
|
Contractor gives Architect all submittals (inspection reports, test reports, record documents, warranties) |
3.11.1 |
List of document types |
| |
|
|
3.12.11* |
Shop drawings, mfg. manuals |
| |
|
|
3.12.12* |
Maint manuals. |
| |
|
|
4.2.9 |
|
| |
|
|
13.5.4 |
Timeliness of delivery |
| 14 |
|
Contractor gives Architect all closeout documents (Affidavit of Payment of Debts and Claims and Consent of Surety) |
9.10.1 |
Prior to final Application for payment |
| |
|
|
9.10.2 |
List of documents |
| 15 |
|
Architect provides all submittals and closeout documents to District. |
4.2.9 |
|
| |
|
|
|
|
| 16 |
|
Contractor submits Application for payment. |
9.3.1.4* |
G702 & G703 |
| |
|
|
9.6.8*, 9.8.10* |
30,60,90 days after substantial completion |
| 17 |
X+30 Days |
Architect issues Final Certificate for Payment |
4.2.5 |
Applications for Payment |
| |
|
|
4.2.9 |
Final completion date |
| |
|
|
9.4 |
W/in 7 days of application |
| |
|
|
9.10.1 |
After receiving documents |
| |
|
|
9.10.1.1* |
Notification |
| |
|
|
9.10.1.2* |
Performance and Document Requirements |
| 18 |
|
District issues final payment |
9.10.2 |
Required documents |
| |
|
|
9.10.4 |
|
19 |
X+12 months |
Architect provides admin. Svcs. During 1 yr. Correction of work period |
2.4.1* |
|
| |
|
|
2.4.14* |
A/E Responsibilities |
STOP WORK |
| |
|
Stop Work |
2.3.1 |
Justifications |
| |
|
Owner to carry out work |
2.4.2* |
Emergencies |
| |
|
Change order to deduct owner's expenses |
2.4.2* |
|
TERMINATION BY OWNER |
| |
|
Valid cause |
14.2.1 |
|
| |
|
Owner complete |
14.2.2* |
7day notice to contractor & Surety |
| |
|
|
14.2.2.2.3.1* |
Not necessarily lowest cost method required |
| |
|
|
14.2.2.2.3.2* |
Costs defined |
| |
|
Deduct/Reimbursement of owner expenses |
14.2.4 |
|
| |
|
Contractor respond |
14.2.5 |
|
| *See supplemental conditions to AIA 201 prepared by Frank Mack |