Crayton Middle School

<<Back

Entire facility is outdated and undersized. Additional space is needed to house programs. Handicap accessibility is inadequate. HVAC system is beyond useful life. Electrical system & support is outdated. Kitchen & cafeteria are inadequate. Gymnasium and support facilities are undersized and are in poor shape. Media 
center, Labs, and Administration areas are inadequate.

Bond Referendum Impact:

  • Crayton will be rebuilt at the present site with a new prototypical middle school facility. The new facility will have a student  capacity of 1,000 and an expected enrollment of 897.

Cost Analysis Enrollment & Capacity
Construction Cost - $16,695,396 Projected Enrollment - 897
FF&E Cost - $1,168,678 Planned Capacity - 1000
Abatement Cost - $333,908
Professional Fees - $2,504,309
Contingency - $834,770
Total - $21,537,061