Alcorn Middle School

<<Back

The parking and drives are inadequate, with some erosion problems. The Media Center is undersized and out-dated. Drama, Band, and Chorus areas are inadequate. There are handicap accessibility  issues. HVAC is beyond useful life. Electrical and Plumbing systems need upgrades. 

Bond Referendum Impact:

  • Additions will include: new Academic Core, Lecture Hall, Band, Drama, and Dance areas. 

  • There will be renovations of the Fine Arts, Media & Cafeteria. 

  • The school will have a permanent capacity of 800 and an expected 
    enrollment of approximately 561.

  • Additionally, the following will be  included: Extensive ADA/Code 
    Compliance Upgrades, Painting, Floor Covering, Ceilings, HVAC Upgrades, Plumbing Upgrades, Electrical System
    Upgrades, Expansion of Data and Communication.

Cost Analysis Enrollment & Capacity
Construction Cost - $14,672,131 Projected Enrollment - 561
FF&E Cost - $1,027,049 Planned Capacity - 800
Abatement Cost - $293,443
Professional Fees - $2,200,820
Contingency - $733,607
Total - $18,927,049